Sketch the layout and check which fixtures can move
Mark the open door, waste stack, drains, shutoff valves and ventilation on your sketch. Add the dimensions of the fixtures you want. Check that the door, drawers and shower screen can open without hitting one another.
For a level-access shower, ask the plumber to check the depth available for the trap and the fall of the waste pipe. If there is too little room, discuss a shower tray before buying the drain. In an apartment block, confirm access to the shared stack with building management.
Work sequence from strip-out to testing
Agree who owns each stage. If different trades are involved, schedule when the plumber will hand over the tested installations to the finishing team.
- Protect access routes, remove old fixtures and finishes, and inspect the exposed surfaces.
- Confirm plumbing, drainage, ventilation and electrical routes. Ask for tests before the installations are enclosed in walls or floors.
- Prepare the substrate and shower fall. Apply the specified waterproofing system and inspect corners, pipe penetrations and the drain connection before tiling.
- Fit the finishes and fixtures, then check drainage, connections, ventilation and maintenance access.
What to include in the quote
A bathroom measuring 1.8 × 2.1 m has 3.78 m² of floor area before fitting out. Wall tiles are measured separately, allowing for tiling height, openings and cuts. Give each contractor the same measurements and photos, and ask who will verify dimensions before ordering.
- Strip-out, protection of common areas, transport and waste removal.
- Substrate preparation and waterproofing, with areas and materials itemised.
- Pipework, connections and fixtures, with responsibility for supply and installation.
- Tiling, cuts around niches, trims, sealants and final tests.
- Payment milestones, how long the bathroom will be out of use, and approval for extra work.
Check the concealed work and inspect the finished bathroom
Ask for photos of the pipe runs and waterproofing before tiling. In the shower, ask how the membrane connects to the drain and how corners and pipe penetrations are treated. The details depend on the products and system instructions.
At handover, run the shower and check for pooling away from the drain. Look over accessible joints, flush the toilet, and open doors and drawers. Record any defects and agree when they will be fixed.
Frequently asked questions
Do tiles and grout waterproof a shower?
The waterproofing layer is installed behind the tiles according to the chosen system. Ask the contractor to specify the materials and details around the drain, corners and pipe openings.
Can I get a firm price from photos alone?
Photos are useful for an initial estimate. A detailed quote needs measurements and an inspection of the substrate and services. Ask what can only be confirmed after strip-out.
What should I choose before work begins?
Choose fixtures that determine dimensions and connections, such as the shower tray, drain or concealed cistern. Confirm models and installation dimensions with the team before ordering.